The Company is a Joint Venture Company with Power Grid Corporation of India Limited and has set up Transmission System comprising of 400 kV Quad Bundle Conductor Double Circuit Line from Karcham Wangtoo HEP Pothead yard at Wantgoo to Abdullapur (219.80 KM), which has been in commercial operation w.e.f. 1st April, 2012 and LILO of Baspa-Naptha-Jhakri Transmission Line (4 KM) that has been in commercial operation w.e.f. 1st June, 2011. The total capital expenditure on the project has been Rs. 1,006.92 crore as on 31.03.2017. The system is operating satisfactorily with cumulative availability of transmission system for F.Y. 2016-17 at 99.96%.